When an agency or end client has not paid, the first question is not who benefited from your work. It is who hired you and promised to pay. A company may have used the deliverable for months while your contract is only with the agency. That can affect who owes the invoice, what evidence you need, and whether approaching the end client helps or complicates the dispute.

The practical response is to map the contracting chain, preserve proof, separate the undisputed amount from any quality dispute, and use a proportionate recovery route. This guide explains the general issues under Indian law. It cannot determine liability without the agreement and communications.

Identify the person or entity that promised to pay

Read the proposal, onboarding form, purchase order, statement of work, invoice, email signature and payment instructions together. Record the exact legal name, address and registration details, where available, of the party that engaged you. A brand name, project manager, agency employee and end client may be different legal persons.

Ask these questions:

  • Who requested the work and approved your quote?
  • Which entity signed, accepted or performed the agreement?
  • To whom did you submit invoices, and who paid earlier invoices?
  • Does the contract say the agency pays you even if its client pays late?
  • Is the agency acting as your principal, a disclosed agent, or only introducing you to the end client?
  • Did the end client separately promise payment, approve a change, or contract directly with you?

The Indian Contract Act, 1872 addresses contracts and agency. Sections 182 and following deal with agent/principal relationships, while section 230 generally sets out when an agent is not personally bound by or entitled to enforce a contract made on behalf of a principal, subject to exceptions. The outcome depends on the documents and the capacity in which the parties acted. Do not conclude that the agency is automatically liable just because its staff sent messages, or that the end client is liable just because it used the work.

Understand what “pay when paid” means in your agreement

Some agency terms say payment to a freelancer is due only after the agency receives payment from its customer. Others give the agency a normal payment deadline and merely explain its billing cycle. The wording, negotiations and surrounding facts determine how the clause operates. Indian law does not give every clause with these words one automatic result.

Check whether the agreement has a fixed outside payment date, whether the agency must invoice or pursue the end client, what happens if the end client disputes or never pays, whether acceptance is in the agency’s control, and whether you can suspend work. Contract Act sections 31–32 address contingent contracts, while sections 37 and 51–54 concern performance and reciprocal promises. These provisions give a framework, but they do not replace interpretation of the actual clause.

If you are negotiating before work starts, propose a clear rule: the agency remains responsible for your invoice by a defined date, regardless of its collection cycle, unless a specific milestone is genuinely conditional. If the client insists on a pass-through condition, negotiate reporting access, a prompt invoice date, a duty to pursue collection, partial payment for accepted work, and a longstop date. For an existing dispute, do not assume that “pay when paid” either defeats or establishes your claim without a lawyer reviewing the clause.

Map the parties and payment promises

PartyWhat to checkWhat it may mean
FreelancerQuote, invoice, accepted terms, deliverablesClaim against the party that engaged you
AgencyContracting entity, payment terms, approvalsMay owe payment under its own promise
End clientDirect messages, purchase order, acceptance, useMay show direct agreement, agency relationship or benefit
Individual contactAuthority, title, company email, conductUsually evidence about the company, not automatic personal liability

Fictional example: Arjun is hired by Brightline Media to edit six product videos for ₹90,000. Brightline gives him the client’s brand guide and approves the edits. Its order form says invoices are due 30 days after acceptance, while a separate footer says Brightline’s payments are “subject to client collections.” The end client posts all six videos and pays Brightline, but Brightline does not pay Arjun. Arjun should first preserve the order form and proof of acceptance, then ask Brightline for the due date and written accounting of the client payment. The end client’s use is useful context, but does not alone prove that it contracted with Arjun. If Brightline never received payment, the conflicting terms still need legal interpretation.

Preserve evidence of scope, delivery and acceptance

Create a chronology with dates, not a narrative of conclusions. Include the initial request, quotation, changes, approvals, delivery, invoice, due date, part-payment, rejection or silence, and later use. Keep emails in exportable form with headers. Retain complete chat exports, file versions, delivery link logs, comments and any proof that the end client published or continued using the work.

Separate four categories:

  1. Agreed scope: what the agency asked you to create and what it excluded.
  2. Approved changes: additions, rush work, extra formats or revisions and who approved them.
  3. Completed work: what you sent, when and to whom.
  4. Payment position: agreed fee, invoice, due date, credits, deductions and amount disputed.

A publication screenshot may help show use, but it does not necessarily establish the fee, acceptance process, or identity of the contracting party. Similarly, an invoice is useful evidence of your demand, but an invoice you created cannot by itself prove the client accepted every term on it.

If the dispute involves electronic communications, the Bharatiya Sakshya Adhiniyam, 2023 governs electronic-record proof in court proceedings. Sections 61–63 address electronic records and their proof. Preserve originals and access to the account or device; do not rely only on edited screenshots.

Send the agency a focused demand

Write to the contracting entity’s official address and the relevant project contact. State the work, agreed fee, delivery and acceptance evidence, invoice number, unpaid balance and requested payment date. If the agency says the end client has not paid, ask for the contract clause it relies on and an update tied to a date. Avoid disclosing the agency’s confidential client documents beyond what is needed to establish your claim.

If the agency disputes quality, ask for a specific list of alleged defects and compare it with the scope and acceptance history. A vague objection after months of use deserves a documented response, but it is still better to address the actual issue than to accuse the agency of bad faith. Offer a reasonable correction only if it fits the agreed scope; do not silently agree to unlimited unpaid revisions.

Keep the demand measured. Do not threaten the end client, post confidential work files, or contact customers as leverage. Those steps can create separate legal and commercial risks. A lawyer’s notice may help where the invoice is material, the agency contests liability or the parties are in different states, but it does not guarantee payment and is not mandatory in every case.

Can the end client be asked to pay directly?

Possibly, but first assess the legal and practical basis. Direct payment may be sensible if the end client expressly hired you, agreed to a fee, gave instructions as a contracting party, or the agency confirms an assignment of the debt. If the agency is your only contracting party, demanding payment from the end client without analysis may be ineffective and may strain a business relationship.

A lawyer may assess whether agency principles, an express promise, assignment, admission, or a restitutionary claim could apply. Section 70 of the Contract Act can matter where a person lawfully provides a non-gratuitous benefit that the recipient knowingly enjoys, but it is not a guaranteed workaround for the absence of a direct contract. The agency’s own role, whether you intended to deal with it alone, the end client’s knowledge, and the nature of the benefit all matter.

Assess the recovery route and limitation

Check the agreement for governing law, court jurisdiction, arbitration and notice clauses. If the agency is an eligible micro or small enterprise supplier and the work qualifies, the MSMED Act may offer an MSE Facilitation Council route. Read our Samadhaan guide, particularly its caution that operational portal requirements and unsettled registration timing need separate analysis.

Ordinary limitation for money claims is often three years, but the applicable schedule article and accrual date depend on the claim and payment terms. Article 18 of the Limitation Act, 1963 specifically addresses work done at the defendant’s request where no payment date was fixed; Article 55 addresses compensation for breach. A reminder or informal promise does not necessarily restart the period. Ask counsel to calculate it from the records, especially if work occurred in stages.

SituationConsiderDo not assume
Agency confirms invoice and asks for timeSigned repayment schedule with datesA verbal extension protects limitation or guarantees payment
Agency says end client has not paidClause wording and proof of collection obligationsEvery pass-through term is valid or invalid
End client used work but never spoke to youEvidence of authority, direct promise and agency relationshipUse automatically makes end client your debtor
Work rejected after publicationAcceptance clause, timeline and specific defectsPublication decides every quality issue
Contract requires arbitrationClause scope, seat, fees and procedural stepsArbitration will be cheaper or faster in every case

Frequently asked questions

The end client used my work for months. Can I invoice it now?

Use may be evidence of benefit or acceptance, but it does not by itself prove a direct contract or agreed price. Identify who engaged you and whether the end client made a separate promise or acted through an authorised agency.

The agency says it cannot pay until its customer pays. Is that enough?

The answer depends on the exact terms, how they were agreed, and surrounding facts. Check for a fixed outside date, acceptance conditions and collection duties. Have counsel review disputed wording before treating the agency’s statement as conclusive.

Can I stop work on other projects for the same agency?

Review each project’s terms and payment status separately. Suspension rights, cross-default and termination clauses may differ. Do not use one overdue invoice to stop unrelated work without understanding the contractual consequences.

Not automatically. A notice should go to parties with a defensible legal connection to the claim. Counsel can decide whether the end client should receive a notice, a document request, or no communication at that stage.

Can I repossess or delete files after delivery?

Do not access the client’s systems or delete delivered work without a clear contractual right. IP ownership and licence conditions may affect future use, but technical self-help can create separate claims. Preserve evidence and seek advice.

What if the agency paid some invoices but not this one?

Earlier payments can help establish the course of dealing, the identity of the payer, and how the parties handled terms. They do not necessarily resolve a new scope or acceptance dispute. Keep each invoice and project record distinct.

Before escalating

  • Name the exact entity that hired you and identify its legal address.
  • Read the signed, emailed or click-accepted terms, including incorporated policies.
  • Preserve scope, changes, approval, delivery, use and invoice evidence.
  • Ask the agency to state its contractual reason for withholding payment.
  • Separate the amount admitted from disputed extras or defects.
  • Check governing law, forum, arbitration, notices and limitation.
  • Get legal review before pursuing an end client or making public allegations.

For future engagements, our freelance contract clauses guide explains how to address payment dates, acceptance, IP and suspension. You can explore contract review workflows, Gotham, or contact the team for product information. These are workflow links, not a promise of legal recovery or case-specific advice.

This article provides general information, not legal advice. The law and procedure may depend on the facts, forum, state, and current rules; consult qualified counsel about a specific matter.